What have I gotten myself into?With the old bathtub cleared away, I tried masking out several different shapes with blue tape.
-
Initial baseboard shape and curb being built from 2x4's
-
Extending the wall
-
Ready for the first layer of cement
Black building paper placed on the baseboard. -
First sloped layer of mortarThis layer goes below the PVC membrane to insure proper drainage, then another layer of cement will go on top of the membrane.
-
PVC membrane in placeFloorpan filled with water overnight to insure there are no leaks.
-
Durock and greenboard installed
-
Second layer of cementThis is the important one that pitches the tile floor just perfectly... it was also a very messy project.
-
Starting to put up tile -
-
-
The finished productIt took some time for the glass to arrive, but overall it was a really cool project!
Custom Granite and Slate Shower
Designed and Built by Steven Heintz
I embarked on a project to build a custom tiled shower from scratch (and photographed my progress along the way)
The project took about three weeks to complete.